JOINT VENTURE SUMMARY
MOUNT CARMEL & OHIOHEALTH
February 2004
COMTEX
Central Ohio Medical Textiles
Land & Buildings

Except for the completion of items on the punch list, the
COMTEX plant is complete. Most of the energy over the past
two weeks have been devoted to the fine tuning of the infra-structure
systems including the boilers, steam regulators, water heating
and reclamation system.
The pictures below set out the state of COMTEX as at January
30, 2004.
Equipment

Equipment systems are now fully installed and in the process
of being commissioned. Although testing, fine tuning, and
adjustments will continue over the next full month, the list
below sets out the state of key operation equipment systems:
- Scales -- Operational
- Cart Dumper -- Operational
- Cart Washer -- Operational
- Soiled Classification System -- Operational
- CBW # 1 & # 2 -- Operational
- Washer Extractors/Dryers -- Not Operational
- Small (Pony) Washers/Dryers -- Operational
- Clean Side Rail System -- 66% Operational
- Feeder/Ironer/Folder Stacker Systems -- Operational
- Small Piece Folders (1-8) -- Operational
- Small Piece Roll Top Tables (1-14) -- Operational
- Take-Away Conveyors (1-2) -- Operational
Budgeting & Finance

Budgeting and finance systems continue to progress and at
the present time historic data covering 2002 and 2003 is being
entered in order to have data from the inception of COMTEX.
It is anticipated that the General Ledger System including
Accounts Payable will be handled in-house by the end of February.
Staffing

Staffing continues to ramp up to take on the start-up of customers.
At the present time COMTEX employs 9 managers and supervisors,
and 23 production staff. Staff receive approximately four
(4) hours of orientation on payroll, policies, systems, and
equipment and then commence their training on equipment.
Health Facility Start-Up Date

Due to the unexpected failure of systems at Doctors Hospital,
COMTEX was requested to go live 24 hours earlier than anticipated.
This enabled the first delivery of product to reach Doctors
Hospital on Sunday, February 1st, requiring staff to work
on the Sunday to prepare for Monday’s order. Thanks
to the efforts of Ed Frilling, Production Manager at COMTEX
and former OhioHealth employee at Victorian Village Health
Center this was accomplished. Set out below are the newest
revised start-up dates for facilities:
- Week of Feb. 8/04 -- Mount Carmel East,
- Friday, Feb. 20/04 -- Grant Medical Center,
- Monday, Feb. 29/04-- Mount Carmel West,
- Week of Mar. 14/04 -- Riverside Hospital.
- Week of Mar. 28/04 -- Marion General Hospital, Morrow
County Hospital, Hardin Memorial Hospital and Galion Memorial
Hospital.
Please raise these dates within your facility to ensure that
everyone is prepared for a seamless start-up of Laundry Service
from COMTEX. |