JOINT VENTURE SUMMARY
MOUNT CARMEL & OHIOHEALTH
June 2003
COMTEX
Central Ohio Medical Textiles
Land & Buildings

Construction has indeed begun at the COMTEX site. At the point
of writing this update, the trenching for the foundation footers
had been completed, and concrete footers had been poured on
the western wall of the building. In addition, internal trenching
for the plumbing and waste water is underway. The steel for
the pre-engineered building has arrived and is being stored
on-site, and the utilities for gas, electric, and water are
also under construction.
The final Gross Maximum Price (GMP) for the project has now
been set at a figure that is approximately $650,000 under
budget. What remains now is to complete the construction as
planned on-time and under budget.
The pictures below show the construction activity at the
COMTEX site on May 21st.
 |
 |
| Click Images to Enlarge |
Equipment

The Board approved the purchase of an additional 150 delivery
carts for COMTEX at the last meeting. The acquisition brings
the total number of Ebco Industries reversible linen carts
to 1,200. This number of carts will greatly improve COMTEX's
ability to provide high quality services to its customers.
Myles Noel, COO, and Amy King, Executive Assistant with the
enlisted help of others from Mount Carmel and OhioHealth,
like Becky Davis and the COMTEX Customer Committee are reviewing
office infrastructure systems. Under analysis at the present
time, are such systems as the computer server and desktop
units, the providers for website systems and the plant devices,
such as the time clock and security systems.
Budgeting & Finance

COMTEX has begun to spend its capital at an increased rate,
with the second Jensen-USA installment for the equipment,
being issued on May 23rd. COMTEX anticipates spending approximately
one million dollars per month over the next several months.
The entire COMTEX project when complete will include member's
start-up contributions of $1,500,000 and financing of $14,085,000
for a total capital investment of $15,585,000.
Staffing

The Human Resource Committee met on Wednesday, May 28th to
review the list of benefits provided by both Mount Carmel
and OhioHealth for the impacted staff, and to design the framework
for the benefit plan for COMTEX. Since COMTEX is not 100%
owned by either of the members and since it will pay its salaries
and wages from revenue earned through operations it does not
qualify to fall under either the Mount Carmel or OhioHealth
benefit plans.
COMTEX hopes to be in a position to tender for employee benefits
during the summer months and to provide the Board with a recommendation
at its September meeting. In addition, the Human Resources
Committee will be presenting their recommendations for key
cost items including staff salary grids, premium pay amounts,
and overtime rates. Once these final two elements are confirmed,
a revised COMTEX operating budget will then be prepared for
Board approval in the first quarter of 2004.
In a global sense the milestones for COMTEX along with progress
towards completion of these key points are as follows:
| |
Milestone |
|
Progress |
| |
Design Building |
|
100% completed |
| |
Select Equipment |
|
95% completed |
| |
Building Construction |
|
5% completed |
| |
Hire Staff |
|
2% completed |
| |
Operate Laundry |
|
To Follow |
|